Designing wells with future intervention in mind is critical for managing well lifecycle OPEX.  New technologies are being delivered by industry to facilitate intervention, especially with the push into 20,000 psi HPHT developments.  Retrofit technologies are also coming to market, enabling light well thru-tubing intervention solutions to problems that formerly required full rig workover.  This session highlights these new technologies and operational developments.
Chairperson
Matthew Vick - bp
Cole Bridges - Llog Exploration Co LLC
  • 1000-1030
    Anchor 20 K Project Overview Of The Completions And Subsea Work Scope
    A. Grimmer, Chevron Corporation
  • 1030-1100
    20,000psi Subsea Intervention: Lessons Learned From The World’s First Offshore Deployment
    B.L. Leinweber, Beacon Offshore Energy; H. Crain, Trendsetter Engineering Inc
  • 1100-1130
    Installation Of Insert WR-SCSSV In Deepwater Gulf Of Mexico Via Riserless Well Intervention Vessel
    C. Prentice, M.E. Mondelli, S. Dennistoun, J. Cubides, BP
  • Alternate
    Umbilical-less Subsea Control System for Completion Installation - Jackup Case Study
    N. Hirsch, P. Otterdal, E. Eide, C. Agar, M. Shenoy, S. Joshi, J.M. Yarnold, OneSubsea